Hot work
[edit] Introduction
The term ‘hot work’ refers to processes that require the use of open flames or that produce sparks through heat and friction that could ignite into a fire. Hot works include:
- Riveting.
- Welding.
- Flame cutting.
- Brazing.
- Soldering.
- Thawing.
- Grinding and drilling (when flammable materials are present).
- Use of any equipment that incorporates a flame.
Hot works can pose a significant fire risk, from both the initial risks of ignition and as a cause of rapid fire spread. According to BS 9999, only if no satisfactory alternative method is feasible should hot work be undertaken.
Precautions should include:
- Carrying out the hot work outdoors or in specially-designated areas that minimise fire risk if possible.
- Scheduling hot works during periods when other works are quieter.
- Applying safe systems for undertaking the hot works.
In 2020, it was reported that research indicated hot works were to blame for 79% of all fires on construction sites in Scotland during the previous year. Ref http://www.constructionmanagermagazine.com/news/construction-firms-warned-hot-works-fire-risk/
[edit] Hot work permit
BS 9999 recommends that a ‘hot work permit’ be followed in order to ensure actions are taken to mitigate and minimise risks before, during and after the works. The permit is appropriate when there are flammable materials in close proximity to the works, and when the work environment is not ordinarily used for such activities.
The permit is used:
- To ensure there is a formal check confirming appropriate work processes are being adhered to.
- To provide time limits for safe working.
- To provide for special PPE (personal protective equipment) or communication methods.
- For coordinating work activities.
- To ensure proper supervision throughout.
When being employed to complete hot works contractors may be required to use the client’s hot work procedure, or they may use a suitable procedure of their own. In the case of the latter, the client must ensure that the contractor is using a suitable hot work procedure.
There are varying levels of risk depending on the type of work and the area within the building that it is taking place. As a result, the hot work permit system should be adapted to the particular needs and risks. In terms of the proposed works, the permit should be designed to provide as much information as possible.
Typically, the hot work permit will identify:
- Administrative details (permit title, number, job location, etc.).
- Description of the work to be undertaken.
- The person/s carrying out the work.
- Likely length of time to complete the work.
- Identified hazards and required precautions.
- Work methods that are required.
- Types of fire-fighting equipment available.
In addition, the permit will identify the requirements that must be met within the work area which include the following:
- Combustible materials removed before work commences.
- Floors swept clean and combustible surfaces covered with heat protections mats.
- Walls covered and combustibles moved away.
- Elimination of explosive atmosphere in the area.
- Removal of flammable liquids and gas cylinders.
- Appropriate screening, protection and display of safety notices.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.